Commercial Solar Interconnection in Georgia: Step by Step

1 day ago
7 min read
Unbranded warehouse with rooftop solar, a pad-mounted transformer and switchgear beside a road lined with pine trees.

Commercial solar interconnection in Georgia is the utility approval that lets a business's solar array run in parallel with the grid, and for Georgia Power commercial and industrial customers it is a seven-step process that ends with a witness test and a Permission to Operate (PTO) letter. In practice, the system size you choose decides which program you can join, which studies and fees you face, and how long the schedule runs. So it pays to screen interconnection before you sign for equipment.

This guide follows Georgia Power's current Behind-the-Meter (BTM) Solar and Storage Interconnection Summary for Commercial and Industrial Customers (revision dated July 31, 2026) and its commercial rooftop FAQ page, both checked on November 16, 2026. Many Georgia businesses buy power from an EMC (electric membership corporation) or a city utility instead of Georgia Power. Their rules differ, and that is covered further down.

The seven steps of commercial solar interconnection in Georgia

Georgia Power lists the same sequence for every behind-the-meter commercial or industrial facility (solar, solar plus battery, or a standalone battery):

  1. Review the summary and the technical documents. These are the Southern Company DER interconnection policy, the Georgia Power BlueBook, the PowerClerk user guide, Distribution Bulletin 18-23 (non-exporting generators), Section G of the Rules and Regulations, and the applicable test policy.

  2. Submit an interconnection application in PowerClerk. The customer or the installer can fill it in, but the agreement is signed by the Georgia Power customer.

  3. Georgia Power reviews the application. The review includes a feasibility analysis of transformer replacements, distribution impacts and schedule implications.

  4. Facility Impact Study, if required.

  5. Sign the interconnection agreement (or a service and interconnection agreement) for the program you chose.

  6. Install the system and pass the local inspection by the Authority Having Jurisdiction (AHJ), usually the city or county building department.

  7. Witness test and PTO. Georgia Power tests safe parallel operation, reprograms the meter if needed and emails the PTO letter.

The most useful line in the summary for a buyer is this one: Georgia Power advises customers not to purchase any facility equipment until it has reviewed the application and decided how the system can connect. Before you submit, you can also ask for a free, high-level feasibility analysis. It is a sensible first screen for any site.

Size thresholds that change the process

Three AC-capacity lines shape most Georgia Power commercial projects:

  • 100 kW. Above 100 kW, every drawing in the application needs a Professional Engineer's stamp. Where no local AHJ exists, a licensed electrician (up to 100 kW) or a Professional Engineer (above 100 kW) must do the required inspections.

  • 250 kW. The Renewable and Nonrenewable Resources (RNR) tariff, which pays for excess energy sent to the grid, is limited to commercial facilities of 250 kW or less. Systems between 100 kW and 250 kW also may not exceed 125% of the premises' metered peak demand from the previous year. Every facility of 250 kW or more must undergo an Impact Study.

  • About 1 MW. The FAQ says a Distribution + Transmission adder study, with a detailed load-flow study, is "typically for systems >1 MWAC".

The 125% rule means a facility with a modest peak cannot size up to 250 kW and still use RNR. The table below applies the rule as written to a few example peaks (illustrative assumptions, not a quote or project data).

Previous-year metered peak demand

125% of peak

Largest RNR-eligible system (kW AC)

70 kW

87.5 kW

100 (the 125% test only applies above 100 kW)

90 kW

112.5 kW

112.5

160 kW

200 kW

200

180 kW

225 kW

225

240 kW

300 kW

250 (tariff cap)

Above those limits, a Georgia Power customer can still build a larger system. It would run as Energy Offset Only (EOO), which pays nothing for exported energy and may require reverse power relays to block export. The other option is to apply as a Qualifying Facility (QF), paid at Georgia Power's actual day-ahead avoided cost under Georgia PSC orders in Docket 4822. This is why the commercial payback math depends so heavily on how much solar the building uses on site.

Fees and studies Georgia Power currently lists

These figures come from Georgia Power's commercial rooftop FAQ as displayed on November 16, 2026. Confirm them at application time, because the utility can revise them.

Item

When it applies

Listed fee

Interconnection fee

Projects ≤ 250 kW AC (RNR or EOO)

$200

Witness test fee

Projects > 250 kW AC (EOO), plus an interconnection fee

$3,900 weekday / $4,400 weekend

Distribution Impact Study

Aggregate on the feeder above 250 kW AC

$1,930

Distribution + Transmission adder

As applicable, typically > 1 MW AC

$5,770

Network Underground study

Sites on a network underground system (common downtown)

$2,400

Reliability study

As applicable, on top of other studies

≥ $220

Adding those up for a 500 kW EOO rooftop with a standard distribution study gives $5,830 on a weekday witness test, before the interconnection fee (set in Section G of the Rules and Regulations) and any grid upgrades. Impact Study costs are paid up front and are non-refundable, whatever the result. The study shows required upgrades but not their price. Upgrade costs depend on the site and appear in the interconnection agreement, and the customer pays them.

Two site conditions deserve an early question to Georgia Power. A building served from a network underground system, which Georgia Power says is mostly found in large metropolitan downtown areas, may not export at all. It must install equipment to prevent export, at its own cost. Sites with delta transformers or campus-style meters, where several buildings sit behind one primary meter, need case-by-case guidance.

What the application package must include

Most avoidable delays come from incomplete paperwork. Georgia Power's summary requires:

  • A digital (not hand-drawn) one-line diagram. It must show the customer name and address matching the account, DC and AC ratings, equipment quantities and models, the AC disconnect location and labeling, the point of interconnection with the meter number, and the point of connection.

  • Spec sheets for modules, inverters and any battery, showing UL 1741 SB and IEEE 1547-2018 listing.

  • Test sheet and nameplate photo for any customer-owned transformer.

  • The DB 18-23 non-export form for batteries that can run in backup mode.

  • A site plan, especially if disconnects are not next to the meter.

  • An IRS W-9.

After installation, the customer must provide a passing final electrical inspection report naming the local AHJ and the permit number. Batteries used for backup need open-transition, mechanically interlocked transfer switches. A battery operating in parallel is also evaluated as added load, which can trigger its own upgrades.

If your Georgia business is served by an EMC or a city utility

Georgia Power's process does not apply to members of Georgia's EMCs or customers of municipal systems. Each utility publishes its own interconnection policy and buy-back rider. Two examples show how different the rules can be:

  • Carroll EMC's distributed generation policy, as filed with the Georgia Public Service Commission, caps non-residential systems at 100 kW. It asks for a $100 application fee at least 45 days before interconnection, promises a decision within 30 days, and buys excess energy at a seasonal avoided-cost rate the co-op can adjust.

  • The City of Cartersville's electric system charges no application fee. It refers to the 10 kW residential and 100 kW non-residential limits of the Georgia Cogeneration and Distributed Generation Act of 2001, and it evaluates larger requests case by case.

Treat these as examples only. Ask your own utility for its current interconnection policy, size limits, buy-back rate and metering charges before you size the system. A 300 kW design that works on a Georgia Power circuit may simply not be allowed on a co-op that caps commercial systems at 100 kW.

Schedule risk: why interconnection timing now matters for tax credits

Interconnection time used to be mainly an annoyance. In 2026 it can affect eligibility for a federal tax credit. IRS Notice 2025-42, issued after the One, Big, Beautiful Bill Act, says the Section 48E clean electricity investment credit and the Section 45Y production credit end for solar facilities placed in service after December 31, 2027, where construction began after July 4, 2026.

A Georgia commercial project that had not begun construction by that date therefore has about 13.5 months from today (410 days from November 16, 2026 to December 31, 2027) to complete application review, any Impact Study, agreements, construction, inspection and the witness test. If a project relies on that credit, its schedule has little room for slippage. Other credit rules also apply, including restrictions on prohibited foreign entities, and projects that began construction earlier follow different deadlines. Confirm eligibility with a tax professional; do not assume the credit applies.

A pre-application interconnection checklist

  1. Confirm your utility: Georgia Power, an EMC or a city system.

  2. Pull 12 months of interval or demand data and note the metered peak.

  3. Decide the program (RNR, EOO or QF), then check the size limits it implies.

  4. Ask for the free feasibility analysis before buying equipment.

  5. Check for network underground service, delta transformers or a campus-style meter.

  6. Budget for study fees and unknown upgrade costs, and add schedule margin for any Impact Study.

  7. If a third party will finance the system under a Solar Energy Procurement Agreement (allowed under Georgia's Solar Power Free-Market Financing Act of 2015), sign that agreement before applying, as Georgia Power recommends.

  8. Line up the building permit and final electrical inspection early. PTO needs the passing report.

Assumptions and limits

This article summarizes publicly posted Georgia Power documents and two example non-Georgia Power policies as they appeared on November 16, 2026. Fees, thresholds and buy-back rules change through utility revisions and Georgia PSC decisions. The RNR sizing table and fee totals are illustrative arithmetic, not a quote or project data. This is not financial, legal, tax, structural or electrical advice. Utility approval, local permits and a licensed contractor are required, and incentives should be confirmed with a tax professional.

More Georgia solar analysis

If you are screening a site, these related ReneEnergy articles go deeper on the next questions:

You can browse every post in the Going Solar category.

Sources

  1. Georgia Power, Behind-the-Meter Solar and Storage Interconnection Summary for Commercial and Industrial Customers, revision 07.31.2026.

  2. Georgia Power, Commercial Rooftop Installations – Frequently Asked Questions (fees, RNR eligibility), accessed November 16, 2026.

  3. Georgia Public Service Commission, Docket 4822 and Docket 16573 (avoided cost and RNR compensation).

  4. Carroll EMC, Distributed Generation Interconnection Policy and Net Energy Metering Rider, as filed with the Georgia PSC.

  5. City of Cartersville Electric, Application for Interconnection of Distributed Generation Facility.

  6. Internal Revenue Service, Notice 2025-42: Beginning of Construction Requirements for Applicable Wind and Solar Facilities.

Fact-checked November 16, 2026.