What is RFNBO? RFNBO stands for "renewable fuel of non-biological origin", the European Union's legal name for hydrogen (and fuels made from it) produced with renewable electricity instead of biomass. Under EU rules, hydrogen only counts as RFNBO if its power meets three tests (new renewable supply, matching in time and matching in place) and it cuts greenhouse gas emissions by at least 70% compared with fossil fuel.

This beginner's guide explains where the term comes from, the three electricity tests in plain words, a worked example of why "hourly matching" matters, and what is still being reviewed in Brussels. It covers the EU only; the US and other countries use different rules.

What does RFNBO mean, and why does the EU need a definition?

RFNBO is the EU's definition of renewable hydrogen, and it exists because the EU has set binding targets that only this kind of hydrogen can meet. The revised Renewable Energy Directive (Directive (EU) 2023/2413, 2023) requires that RFNBOs make up at least 42% of the hydrogen used in industry by 2030 and 60% by 2035. In transport, advanced biofuels, biogas and RFNBOs together must reach 5.5% in 2030, with at least 1 percentage point from RFNBOs.

Targets like these only work if everyone agrees what counts. Without a definition, a plant could run on fossil-heavy grid power and still call its hydrogen "green". The RFNBO rules close that gap. "Non-biological" simply separates these fuels from biofuels, which follow their own rules.

What are the three electricity tests for RFNBO hydrogen?

The three tests are additionality, temporal correlation and geographical correlation, set out in Delegated Regulation (EU) 2023/1184 (2023), checked on EUR-Lex on November 20, 2026. In plain words:

Test

The question it asks

Rule in the 2023 text (date or limit)

Additionality

Is the electrolyzer using new renewable power, not power others already use?

Renewable plant came into operation no earlier than 36 months before the electrolyzer

Temporal correlation

Was the renewable power produced at the same time the hydrogen was made?

Same calendar month until December 31, 2029; same hour from January 1, 2030

Geographical correlation

Was the renewable power produced in the same grid area?

Generally the same bidding zone (with limited exceptions for connected zones)

There are shortcuts. If the electrolyzer is wired directly to its own wind or solar farm with no grid power, it qualifies through the direct-connection route. If a bidding zone's grid was more than 90% renewable in the previous calendar year, grid power can count as fully renewable. And in any hour when the day-ahead power price is at or below €20 per MWh (or below 0.36 times the EU carbon allowance price), the time-matching test is treated as met.

There is also a transition period: electrolyzers that come into operation before January 1, 2028 are exempt from the "new renewable plant" condition until January 1, 2038. The European Commission's renewable hydrogen page describes this as letting producers sign long-term power purchase agreements with existing renewable plants until 2028.

Why does hourly matching make such a difference?

Hourly matching matters because a plant that runs around the clock on solar power can pass a monthly test and fail an hourly one. Here is our own illustrative example (simplified numbers, not a real project):

  • A 10 MW electrolyzer runs 24 hours a day, so it uses 240 MWh of electricity per day.

  • It buys power from a solar farm that delivers 30 MWh per hour for 8 daylight hours, also 240 MWh per day.

Matching rule

Electricity used (MWh/day)

Renewable power counted (MWh/day)

Share that counts as matched (%)

Monthly (rule until end of 2029)

240

240

100

Hourly (rule from 2030)

240

80

33

Under monthly matching, the totals balance, so all 240 MWh count. Under hourly matching, only the 8 sunny hours count, and only up to the 10 MWh the electrolyzer uses in each of those hours: 8 × 10 = 80 MWh, or one third. To stay fully renewable, the plant would need to run only when the sun shines, add wind or storage, or buy from several sources whose output covers the night.

What is the 70% emissions rule for RFNBO?

On top of the electricity tests, RFNBO hydrogen must achieve at least 70% greenhouse gas savings over its life cycle, according to the European Commission. The calculation method is in Delegated Regulation (EU) 2023/1185 (2023), which sets the fossil fuel comparator at 94 grams of CO2-equivalent per megajoule (g CO2e/MJ).

A quick calculation turns that into a number per kilogram:

  • A 70% saving on 94 g CO2e/MJ leaves at most 28.2 g CO2e/MJ.

  • Hydrogen's lower heating value is 51,585 Btu per pound according to the US Department of Energy's Alternative Fuels Data Center, which converts to about 120 MJ per kilogram.

  • 28.2 g/MJ × 120 MJ/kg ≈ 3.38 kg CO2e per kg of hydrogen.

So, as a rule of thumb (our arithmetic, not an official figure), RFNBO hydrogen must stay below roughly 3.4 kg CO2e per kilogram across its whole supply chain. That life-cycle count includes upstream emissions, grid electricity, processing and transport to the user.

How do producers prove their hydrogen is RFNBO?

Producers prove compliance through certification by independent schemes that the European Commission has recognised. For example, Commission Implementing Decision (EU) 2024/3180 of December 19, 2024 recognised the CertifHy scheme for demonstrating that consignments of RFNBOs meet the 2023/1184 rules, valid until December 21, 2029. The Commission says EU countries must accept evidence from recognised schemes.

In practice, certification means metering, power contracts and audits. A certifier checks the electrolyzer's hourly or monthly power use against the renewable power it bought, the age and location of the renewable plants, and the emissions calculation.

Are the RFNBO rules about to change?

A targeted review is under way, but as of our check on November 20, 2026, the 2023 text is still the law. The Commission's renewable hydrogen page lists only the review scheduled for July 2028 and no amendment. An industry analysis by HYZ Energy dated October 12, 2026 reported that the Commission had announced the review in April 2026 but had not yet published a draft, and that member states and industry were asking to delay hourly matching and the additionality cut-off, in some proposals to 2035.

For a beginner, the safe reading is: the three tests and the 70% rule are in force; the dates (2028 and 2030) are the parts most likely to move. Always check EUR-Lex for the current text before relying on a date.

Where do the RFNBO rules not fit?

The RFNBO label is not a measure of whether hydrogen is the right tool. It certifies how hydrogen was made, not whether it should be used. Where electricity can do the job directly, such as cars, home heating or most low-temperature heat, using the renewable power directly is usually more efficient than turning it into hydrogen first. The rules also add real compliance work, so very small or experimental projects may find certification hard to justify. And outside the EU, other definitions apply, so "RFNBO-compliant" and "green" in another market may not mean the same thing.

Screening a real hydrogen project?

If you are weighing an actual site, the power supply choice drives both cost and certification. Our H2Hub guide to grid-connected vs off-grid electrolysis works through a 100 MW example under EU and US rules. You can start a project without an account or card, and your first full project report is free per account: Start a free project screen in H2Hub.

Frequently asked questions

Is RFNBO the same as green hydrogen?

Not exactly. "Green hydrogen" is an informal term with no single legal meaning. RFNBO is the EU's legal category, with specific tests for electricity sourcing and a 70% emissions saving, so all RFNBO hydrogen is renewable, but not everything sold as "green" meets the RFNBO rules.

Does blue hydrogen count as RFNBO?

No. Blue hydrogen is made from natural gas with carbon capture, so its energy does not come from renewable sources, which the RFNBO definition requires.

When does hourly matching start for RFNBO?

Under the 2023 text, monthly matching applies until December 31, 2029 and hourly matching from January 1, 2030. That date is part of the ongoing review, so check the current text before planning around it.

Can grid electricity be used to make RFNBO hydrogen?

Yes, if the producer holds renewable power purchase agreements and meets the time and location matching tests, or if the bidding zone's grid was more than 90% renewable in the previous year.

Related reading

Sources

  1. European Union, Commission Delegated Regulation (EU) 2023/1184 (RFNBO electricity rules), EUR-Lex, checked November 20, 2026.

  2. European Union, Directive (EU) 2023/2413 (revised Renewable Energy Directive), Articles 22a and 25, EUR-Lex.

  3. European Union, Commission Delegated Regulation (EU) 2023/1185 (greenhouse gas methodology), EUR-Lex.

  4. European Commission, Renewable hydrogen, checked November 20, 2026.

  5. European Union, Commission Implementing Decision (EU) 2024/3180 recognising the CertifHy scheme, December 19, 2024.

  6. US Department of Energy, Alternative Fuels Data Center: Fuel Properties Comparison.

  7. HYZ Energy, RFNBO Delegated Act Revision 2026: What Could Change, October 12, 2026 (industry analysis).

Fact-checked November 20, 2026.

Recent Posts

See All

Comments


Technical films · About · H2Hub · Hydrogen industry directory · Blog · Shop · Feasibility template · Privacy policy · Affiliate disclosure · Contact

As an Amazon Associate, ReneEnergy earns from qualifying purchases.

bottom of page